Sunshine Silver Targets 2028 Production Return as Mine Prep Progresses

MixedMedium impact

Sunshine Silver Mining & Refining Company (SSMR) announced progress on its mine preparation, underground development, and site infrastructure work. The mining company expects to complete a formal feasibility study in the second quarter of 2027 and is aiming to restart full commercial production in late 2028.

During the first half of 2026, the company completed roughly 1,200 meters of underground development, with another 1,300 meters scheduled before year-end. Crews have also laid about 1,200 meters of underground rail track to bolster logistics and safety, with plans for 1,900 meters more. On the surface, demolition of an old processing mill that began in 2025 should wrap up by the end of 2026, freeing space for a new processing facility. The planned plant will handle approximately 1,000 tonnes per day initially, with capacity to upgrade to 2,000 tonnes per day.

Investors should monitor upcoming exploration and site milestones through the end of the year. The company has completed about 47,600 meters of a 50,000-meter infill drilling campaign as of September 30, 2026, and plans to release additional drilling data before 2027. It is also continuing shaft and hoist upgrades following the commissioning of a new production hoist at the Jewell Shaft earlier this year.

Key points

  • Sunshine Silver Mining & Refining Company (SSMR) targets a feasibility study in Q2 2027 and a production restart in late 2028.
  • The company completed about 47,600 meters of its 50,000-meter infill drilling program as of September 30, 2026.
  • Underground work included roughly 1,200 meters of development and 1,200 meters of rail installation in the first half of 2026.
  • Mill demolition is scheduled to finish by year-end, clearing space for a new plant designed for 1,000 to 2,000 tonnes per day.

Written by our AI from expert market sources across the web. It can contain mistakes: check the facts before acting on them. Write-ups powered by the free AI API at FreeTheAI.org

How we writeDisclaimer

Questions and answers

When does Sunshine Silver plan to restart production?

Sunshine Silver Mining & Refining Company targets a return to production in late 2028, following the scheduled completion of a feasibility study in the second quarter of 2027.

What is the capacity of Sunshine Silver's planned new processing plant?

The new processing facility will be sized for approximately 1,000 tonnes per day initially, with design capabilities allowing an upgrade to roughly 2,000 tonnes per day.

What drilling progress has Sunshine Silver completed so far in 2026?

As of September 30, 2026, the company completed about 47,600 meters of a 50,000-meter infill drilling program, with additional drill results expected before year-end.